WILTON ROAD, READING RG30 2SS

Purchase Price

£300,000

Stamp Duty & Legal Fees

£21,400

Date of Purchase

March 2025

Project & Build Investment:

Turn-Key Service Fees

£42,000

Consultant & Compliance Fees

£12,000

Refurbishment & Build Costs

£140,000

2nd fix & Furnishings

£30,000

Total Start-Up Cost

£224,000

Key Metrics

Estimated Value

£600,000

Estimated Gross Yield

10.98%

Estimated Cash-on-cash Return

19.15% per annum

All Money Back in approximately

5.2 Years

Gross Monthly Rental

approx. £4,950

Monthly Profit

approx. £1,900

Before

3 Beds | 1 Bath | 2 Receptions

A modest mid-terrace property with a practical footprint and strong potential for HMO refurbishment and modernisation.

After

6 Beds | 6 Ensuites | HMO

Wilton Project now presents as a modernised six-bedroom HMO, combining refreshed interiors with practical upgrades throughout.

Renovations Made

RPG took a targeted refurbishment approach, reworking the property into a 6-bed, 6-en-suites HMO configuration while focusing on practical improvements to layout, safety, comfort and presentation.

Space reconfiguration

Selected openings and internal layouts adjusted to improve circulation and accommodate the new room configuration.

Fire & safety

FD30 fire-rated doors with intumescent strips, PIR emergency lighting and associated safety upgrades.

Building services

Radiators repositioned, additional sockets installed, lighting upgraded and plumbing works carried out.

Bedrooms

New flooring, decoration, electrical points and practical detailing throughout.

Communal areas

Kitchen and dining spaces refreshed with painted units, new worktops and updated lighting.

Bathrooms

Vanity units, mixer taps, towel rails and waterproof finishes introduced as part of the refurbishment.

Finishes

New carpets, laminate and vinyl flooring, plasterboarding, skimming and full decoration.

Final delivery

Snagging and finishing works completed to bring the property together as a cohesive HMO.

Our Work in Focus

Historical figures from a specific project and period. Results are not representative of all projects and are not indicative of future performance. Figures may depend on assumptions, financing arrangements, operating costs, occupancy, market conditions and other project-specific factors.